Hangzhou Tianyuan Building Co., Ltd. regarding “Central Air Conditioning Unit No. 1 of Tianyuan Building” PC05 Controller UCM and 2 Repair of the Phase Sequence Protector for Unit No. [Number] Conduct single-source negotiations. Details are as follows:
1 Tender No.: TYDS-2021-016
2 Project Name: Central Air Conditioning Fault Repair at Hangzhou Tianyuan Building
3 Project Overview: Central Air Conditioning Unit No. 1, Tianyuan Building PC05 Controller/UCM failure replacement and No. 2 unit phase sequence protector failure replacement and repair.
4 Funding source: Self-funded with own capital.
5 Construction period requirements: No more than 20 days shall elapse from the date of contract signing.
6 Contracting Method and Scope of Contract:
(1) Lump-sum construction contract: covers labor, materials, quality, schedule, and safe and civilized construction.
(2) Scope of Contract: Air conditioning units No. 1 and No. 2
7 Specific construction requirements: Replace the faulty components.
8 Qualification requirements for eligible bidders:
(1) Bidders shall be registered within the territory of the People’s Republic of China and possess independent legal personality.
(2) This project does not accept bids submitted by consortia.
9 · Engineering quality requirements: Construction shall be carried out strictly in accordance with the current national construction and acceptance specifications, quality inspection and evaluation standards, relevant documents issued by the national industry authorities guiding engineering construction, and the contents of the tender documents. The quality of the project must meet the standards specified in the "Code for Acceptance of Construction Quality" and the GB 50016-2006 Code for Fire Protection Design of Buildings. The warranty period for quality assurance is two years.
10 Material Brand Requirements : McQuay or the manufacturer designated by McQuay
11 Construction site inspection time: On-site inspections will not be conducted in a unified manner; each bidding unit will conduct its own inspections.
12、 There will be no centralized Q&A session prior to bidding. Any questions from bidders will be answered by the procuring entity and provided in a unified written response.
13 Bidding method: Single-source negotiation
14. Registration Period:
(1) Time: 2021 _11 Moon 17 As of 2021 11 Moon _22 Closed on Sundays (working hours: 9:00 a.m. to 11:30 a.m. and 2:00 p.m. to 4:30 p.m.).
(2) Location: Engineering Department, Tianyuan Building, No. 2 Qianchao Road, Hangzhou City
(3) Provide a copy of the business license of the legal entity.
15 Bid opening time: 2:00 p.m. on November 22, 2021
16 Composition of the Bid Evaluation Committee: An odd number of three or more people.
17 Evaluation Method:
18、 Maximum price: RMB 40,000 (in words: Forty thousand yuan)—Bids exceeding the maximum price limit will be deemed invalid.
19 Contact information:
Tendering Entity: Hangzhou Tianyuan Building Co., Ltd.
Contact: Engineer Ye (13588095013)
Hangzhou Tianyuan Building Co., Ltd.
2021 November 16 of the year